Is there a way to set up a task template where we can set items to be completed in the future. IE 

task one due today

task two due 7 days from start of project etc etc?

 


This topic has been closed for comments

1 reply

Userlevel 1

I wish this functionality was in Project templates, but I haven’t found a way to do it in them. The “due date” field in a card/task on a project template is useless without some way to set a relative date.

 

There is a way to accomplish this in Workflow Automations, using the DATEADD() formula. Here’s a screenshot for how I set one of them up: